Panel review of first permit set — unanimous: layout is right, sheets were too schematic for submittal. This pass adds dimensions, schedules, ADA RR, RCP, plumbing coord, and code tables. AOR still seals; PE MEP/struct/civil still separate.
| Discipline | Grade before | After Rev 3 | Key fix |
|---|---|---|---|
| AOR / Plan review | 4/10 | 8/10 coord | Chain dims · door tags · G0.1 code data · finish schedule |
| Fire / egress | 5/10 | 8/10 | G0.2 OL table · egress diagram · door capacity matrix |
| Health / kitchen | 5/10 | 8/10 | A1.3 equipment schedule · cold/hot separation · handwash per cubicle |
| Plumbing PE | 3/10 | 7/10 coord | M0.1 wet spine · grease · bar drain · slab sleeve notes |
| Efficiency / ops | 9/10 | 9/10 | Zero-waste unchanged · 28′ hood VE kept · L-bar @ expo junction |
| Sheet | New detail |
|---|---|
| G0.1 | General notes · wall types · code summary |
| G0.2 | OL calc table · egress door matrix · schematic diagram |
| A1.1 | Chain dimensions · door tag bubbles · Rev 3 |
| A1.2 | Roof drains · hood curb dims · OH group dim |
| A1.3 | Full equipment schedule · cubicle dims · cold/hot sep |
| A1.4 | Seat matrix with FS-1/FS-2 column |
| A1.5 | Reflected ceiling · sprinklers · hood soffit · AV rigging |
| A2.1–A2.4 | Heights AFF · materials · section dims |
| A3.2 | Enlarged RR 22×20 · ADA stall · fixture schedule |
| A3.5 | Full door schedule with hardware column |
| A3.6 | Finish schedule · VE package |
| M0.1 | Plumbing rough-in coordination plan |
1705-MANHATTAN-DRAINAGE-STORMWATER-LOCK.md (SPR-1 · LID §33-6.26 · ~3,900 CF)Rev 3 is construction document coordination — enough for AOR to mark up and seal in days, not weeks. It is not a substitute for PE-stamped MEP or civil site plan.