← GC bid sheet Build package

MEP · Plumbing · Fire · HVAC · Electrical · Brief by SF

1705 Manhattan · Concept 2D · Rev 9 · Every wet, fire, and mechanical facet tied to zone + square footage. Cross-ref GC bid lines · constants concept_2d_pemb_constants.py

Kitchen SF · read this first — NOT one 1,260 SF room

1,260 SF = cloud kitchen BOH only (42×30 NW corner). All cooking, hood, grease, walk-in, and dish happen here. The guest-facing Six Chef Hall is a separate 60×60 · 3,600 SF zone — dining, bar, pickup windows, roll-ups. No grease cooking in the chef hall.

ZoneDimensionsSFWhat happens hereModel
Cloud kitchen BOH42×301,2606 cubicles · 28′ Type I hood · walk-in · dish · grease · RR-3Production / commissary
Six Chef Hall60×603,6006 concepts @ CO · pickup PU-1–6 · bar · seating · 3 roll-ups → lawnFront-of-house · no hood
Total food service footprint~4,860BOH cooks → passes through windows → guest eats in chef hall
Mirage Ballroom (A-2 assembly)75×604,500299 OL · events · no kitchenSeparate · uses RR-1
A-2 total (code / parking)8,100Chef hall 3,600 + ballroom 4,500 · “one kitchen line” = one BOH feeds both

Is 1,260 SF enough for 6 concepts? Only because this is a cloud/ghost kitchen — one shared BOH, ~210 SF per cubicle, one hood line. Not six standalone restaurants. PE + health dept size hood, grease interceptor, and cubicle count. If you need six full independent kitchens, scope and budget change materially.

Building area summary

PEMB footprint16,800 SF200′×84′ · 3 stories
L1 slab (occupied)~12,000 SFminus 120×40 court void
L2 + L3 hotel~16,128 SF48 × 336 SF rooms
Sprinkler protected~50,400 SF16,800 × 3 levels
AreaDimensionsSFRoof / slab
PEMB building pad200′ × 84′16,800One roof · L1 slab under shell
Open court void (center)120′ × 40′4,800No roof · no slab · turf @ grade
L1 net slab pour~12,00016,800 − 4,800 void
Event lawn (turf in void)120′ × 40′4,800Outdoor · drain to civil
Plunge pool water15′ × 35′525Outdoor · key-gated
Stage deck32′ × 12′384Outdoor · north axis
Palm court (site north)203′ × 80′16,240Accessory · strings · landscape
Parking bowl120 stalls~45,000Site · storm to SPR-1

L1 · zone-by-zone · SF + every MEP/plumbing facet

Zone Dim SF Plumbing HVAC Electrical Fire / sprinkler Bid line Target $
Cloud kitchen BOH 42×30 1,260 Floor sinks · 3-comp · hand wash ×6 · walk-in cond drain · dish · grease waste to interceptor · RR-3 adj 28′ Type I hood package — canopy · grease duct · roof fan · makeup air · startup/balance · walk-in cond · line heat Kitchen panel · walk-in · hood lights · fan · Ansul circuit NFPA 13 plenum heads · Ansul R-102 install · heat detectors @ hood · fusible links 9.03 · 22.04 · 23.03 · 11.01 · 21.01 $81,000*
Six Chef Hall 60×60 3,600 Floor drains · bar sink · soda/ice · 6 pickup lines to PU windows · no grease in dining (kitchen BOH only) RTU zone · high exhaust from west hood path · 3 roll-ups to lawn Track lights · kitchen pickup · roll-up motors Sprinklers @ 16′ exposed deck · assembly path to 299 w/ ballroom 9.02 · 23.01 · 8.02 incl
Grand Arrival Hall 75×36 2,700 Bar sink · ice · soda · floor drain @ bar · uses RR-1 (not in zone) RTU · destrat fans · no drop ceiling Bar · portal sign · uplight · D-01 glass Sprinklers · FA horn/strobe 9.01 · 12.01 · 9.08 incl
Concierge alcove 18×14 252 Hand sink optional · floor drain RTU spill · PTAC N/A Check-in · low voltage Sprinklers 9.01 incl
Mirage Ballroom 75×60 4,500 Floor drains · mop · no kitchen grease · uses RR-1 public RTU large zone · 299 OL load · roll-up to lawn Stage AV power east spine · drape uplight · egress lighting Assembly OL 299 · sprinklers · FA · egress doors D-65–68 9.04 · 12.02 · 26.01 incl
Retail × 10 25×30 ea 7,500 No suite RR @ CO · floor drain shell · tenant sink rough 3 lease-ready only RTU or split per PE · 3 finished bays base heat/cool 10 court doors · 3 lease-ready circuits Sprinklers all bays 9.05 · 9.06 · 8.03 incl
RR-1 public 18×12 216 4 WC · 2 lav + ADA · mop sink · hot water from central WH Exhaust fan · not HVAC conditioned hard Lighting · hand dryer circuits Sprinklers · FA 22.01 16,500
RR-2 court/retail 18×12 216 4 WC · 2 lav + ADA · serves RT-01–10 + lawn Exhaust fan Lighting Sprinklers 22.02 15,500
RR-3 employee 8×10 80 2 WC · 2 lav · BOH staff only · lock Exhaust · FRP zone Light Sprinklers 22.03 5,500
Elev + core chase 10×10 100 Floor drain @ pit · sump if req Shaft vent · elevator machine room HVAC Elevator feed · riser panels Shunt trip · sprinklers in shaft per code 9.07 · 26.01 55,000
L1 program total (zones) ~20,324* *Zones overlap in bar geometry · 12,000 SF actual slab pour Lines 9.xx · 22.xx

L2 + L3 · hotel · 48 keys · RM-1 12×28 = 336 SF each

LevelKeysRoom SFLevel SFPlumbingHVACElectricalFireBid lineTarget $
L224336 ea8,064 24 in-room baths 3×8 wet · stacked risers west spine · tub/shower · vanity 24 PTAC sleeves @ rough 24 room circuits · corridor egress · card lock Sprinklers · FA · rated corridor 9.10 · 9.11 · 23.02190,000
L324336 ea8,064 24 in-room baths · stacked wet walls 24 PTAC 24 room circuits Sprinklers · FA 9.10 · 9.11 · 23.02190,000
Corridors L2–L3~2,400 Floor drains · hose bib BOH Corridor exhaust/pressurization per PE Egress · emergency Sprinklers · FA 9.12incl
48 keys total ~18,528 48 WC · 48 lav · 48 tub/shower · ~1,152 SF wet total 48 PTAC 48 doors · 48 windows Full NFPA 13 both floors 9.10–9.11 · 22.04*380,000

*Hotel bath rough/trim priced in 9.10 + 9.11 · not separate RR lines · NOT in RR-1/2/3 public schedule.

Site · outdoor · wet + fire

ZoneSFPlumbingElectricalFireBid lineTarget $
Plunge pool 15×35 + equipment525 + equipPool feed · drain · filter · auto-fill · key gatePool pump · light · timerBarrier · bond per code2.07 · 3.0322,000
Event lawn turf4,800Area drains to storm · no sanitary2.088,000
Stage + projector screen384 + bandStage AV · screen · uplight2.0910,000
Grease interceptor (west spine)Central grease trap/interceptor · all kitchen + hood waste · sized 6 concepts · pump if req · cleanout accessAlarm if req22.05 · 2.049,500
Stormwater SPR-1~1.89 acDetention ~3,900 CF · LID · parking + roof runoff2.0535,000
Utility stubs to buildingWater meter · sewer tap · grease line · pool line400A service stub · commFire dept connection FDC @ sprinkler2.04 · 26.0128,000+

*Cloud kitchen BOH 1,260 SF total target: build-out 9.03 $25k · plumbing 22.04 $18k · hood/exhaust/Ansul 23.03 $28k · cooking line equip 11.01 $35k · sprinkler hood tie-in in 21.01. Hood exhaust installation is IN scope — not owner-furnished.

Kitchen hood · exhaust · makeup air · Ansul · full install scope

Yes — included. Bid line 23.03 · $28,000 is a turnkey Type I commercial kitchen ventilation package for the 42×30 · 1,260 SF cloud kitchen BOH. Separate from cooking equipment (11.01 $35k) and kitchen plumbing/grease (22.04 $18k + 22.05 $9.5k).

ItemSpecQty / SFInstall includesBid lineIn $28k?
Type I hood canopy28′ linear · stainless · over 6 cook lines28′ · 1,260 SF BOHSupply · hang · level · lights · filters · access panels23.03Yes
Grease exhaust ductWelded steel · code slope · cleanoutsBOH → roofFabricate · insulate where req · west spine path · roof penetration23.03Yes
Roof exhaust fanUpblast · sized to hood CFM1Fan · curb · weather cap · vibration isolators · wiring to panel23.03Yes
Makeup air (hood)Dedicated MUA or interlocked supply1,260 SF BOHUnit or ducted MA · fire damper if rated · interlock w/ exhaust fan23.03Yes
Hood grease wasteFrom hood · trough · floor sinks1,260 SFDrain to grease interceptor west spine22.04 · 22.05Separate $27.5k
Ansul / hood suppressionR-102 or equal · UL 3001 systemNozzles · tanks · manual pull · auto fuel/electric shutoff · full install + test23.03Yes
Sprinkler in hood plenumNFPA 13 wet · hood tie-in~50,400 SF bldgHeads in hood · shunt if req · FDC at riser21.01In $52,080
Heat detectors / FA@ hood · link to FA panel1,260 SFDetectors · horn/strobe path · addressable tie-in26.02 · 23.03Yes
Startup / balance / testCFM · capture · Ansul · interlocks1Commission · TAB report · health dept ready23.03Yes
Chef hall spill exhaustOdors from pickup windows · not Type I3,600 SFGeneral exhaust path from west hood route · RTU zones23.01In $52k RTU
Cooking line equipmentRanges · fryers · prep · cold · all-electric6 conceptsNOT in hood line — under hood only11.01$35,000
Walk-in cooler/freezerRefrig unit + cond drain1 · 1,260 SFBox + cond · drain in 22.04 · power in 26.019.03 · 11.01In build-out
Kitchen ventilation + fire package subtotal$28,000 + $52,080 sprinkler + $27,500 grease/plumb

Not included @ CO: gas piping (all-electric kitchen) · tenant hoods in retail bays · Phase 2 additional hoods · hood cleaning service contract (owner O&M).

Master fixture & device count · all plumbing-related

Sanitary / domestic
Public WC stalls (RR-1 + RR-2)8216+216 SF RR rooms
Employee WC (RR-3)280 SF
Public lavatories4 + ADARR-1 + RR-2
Employee lavatories2RR-3
Hotel in-room WC483×8 wet × 48 = 1,152 SF wet
Hotel in-room lav/tub-shower48 eachInside RM-1 336 SF
Floor drains / trench (kitchen)6+Cloud kitchen 1,260 SF + chef hall
Hand wash (kitchen/code)8+BOH + chef lines
Bar sinks2Grand Arrival + chef hall bar
3-comp / dish1Cloud kitchen
Walk-in cooler/freezer drain1Cloud kitchen
Mop sinks1–2RR-1 + BOH
Water heaters1 bankServes hotel 48 + kitchen + RR
Pool equipment1525 SF pool
Grease · fire · mechanical
Grease interceptor / trap1West spine · all Type I waste
Type I hood canopy28′Cloud kitchen 1,260 SF · line 23.03
Grease exhaust duct + roof fan1 runBOH west spine → roof · line 23.03
Hood makeup air unit1Interlocked w/ exhaust · line 23.03
Ansul / hood suppression (installed)1 systemFull install + test · line 23.03
NFPA 13 sprinklers~50,400 SF16,800 ftpr × 3 levels
Fire alarm devicesfull bldgHorn/strobe · addressable
RTU / makeup air (L1)multi~12,000 SF L1 zones
PTAC (hotel)48336 SF × 48 rooms
Hood exhaust fan (roof)128′ hood · line 23.03 · installed
RR exhaust fans3RR-1 · RR-2 · RR-3
Electrical service400A minWhole building + site
Fire dept connection (FDC)1Sprinkler riser
Pickup windows PU-1–66Chef hall → court

Wet spine · west BOH · one path for all heavy plumbing

Before slab pour (line 3.01): sleeve under slab on west utility spine — domestic hot/cold · sanitary · grease waste to interceptor · vent stack · kitchen trench drains · hotel stacked risers L2/L3 · sprinkler main · electrical conduit to kitchen panel.

East spine: ballroom AV · stage power · low voltage · FA homerun to panel.

Core 10×10: elevator · sprinkler riser · electrical riser · HVAC shaft.
SystemServes SFRouteBid $
Sanitary + grease1,260 + 3,600 kitchen zonesWest spine → grease interceptor → sewer22.04–22.05 · $27,500
Domestic water + hot~30,000 SF buildingWest spine · central WH22.06 · $9,000
Hotel wet stacks48 × 336 SFWest spine · stacked L2/L39.10 · incl
Sprinkler main + branches~50,400 SFCore riser · tee all levels21.01 · $52,080
Hood Ansul + exhaust install1,260 SF BOH28′ hood · duct · fan · MUA · suppression23.03 · $28,000

MEP bid totals · cross-ref GC bid sheet

TradeScope summarySF basisMirage targetMarket
PlumbingRR-1/2/3 · kitchen · grease · WH · 48 baths · pool~12k L1 + 18.5k hotel + site$74,000$125,000
HVAC / ACL1 RTU + makeup · 48 PTAC · 28′ hood exhaust~12k L1 + 16k hotel$117,440$208,000
Electrical400A · all zones · court · sign · stage · kitchen · hotelFull building$68,000$115,000
Fire alarmAddressable horn/strobe entire building~50,400 SF$11,500$18,000
Sprinkler NFPA 13Wet system · hood tie-in · FDC · 3 stories16,800 × 3$52,080$88,000
Kitchen hood + Ansul28′ Type I · exhaust · makeup · suppression1,260 SF BOHin 23.03 · $28,000$48,000
Grease interceptorCentral · west spine · 6-concept size$9,500$16,000
MEP + fire subtotal$332,520$572,000

Full GC bid including shell, site, build-out, FF&E: $2,575,000 target → beat this