Prices below = Louisiana Gulf South low end (Jefferson Parish · owner-build / aggressive PEMB path · Jul 2026 research). Your job: bid lower and still deliver every line.

MIRAGE TARGET · $2,575,000 GC MARKET TYPICAL · ~$3,850,000 ALL-IN W/ LAND · $3,000,000 cap
Mirage target (GC scope)
$2,575,000
Beat this · excl. land
LA market typical
~$3,850,000
Turnkey contractor · same scope
Your bid $
________
Fill column · must match scope

Louisiana low-end research · Jul 2026

Sources: LA ~14% below US avg (CostFlowAI) · PEMB shell $14–30/SF package · NOLA turnkey PEMB $35–60/SF installed (Red Iron Buildings) · Commercial new $215–415/SF typical / we build lean · Hotel market $80k–250k/key · Mirage path = PEMB + repeat LGS × 48 @ ~$8,333/key installed vs market $45k–65k/key turnkey · Restaurant TI $275–530/SF typical / we VE to stained slab + hood · Skilled labor ~$39/hr LA avg.

How Mirage hits low: one PEMB shell · open court (no roof over 4,800 SF) · zero drop ceilings · black-box ballroom · 6 chefs but lean equipment · owner GC · repeat room type × 48 · shell retail + 3 finish only.
BenchmarkMarketMirage target
Hotel room build + FF&E (48 keys)$45,000 – $65,000 / key$11,417 / key ($380k + $168k FF&E)
PEMB 3-story 200×84 shell + erect$1,400,000 – $1,650,000$900,000
Slab-on-grade ~12,000 SF$22 – $28 / SF$16.42 / SF
Parking stall surface$1,200 – $1,800 / stall$850 / stall
Plunge pool 15×35 turnkey$35,000 – $55,000$22,000
Commercial kitchen 6-concept$120,000 – $180,000$69,000

Line-item schedule · Mirage target filled · you beat it

Every row = exact Day 1 @ CO scope. Mirage Target $ is our floor. Market Typical $ is what Louisiana contractors usually quote. Write your number in Your Bid $ — lower wins if scope is complete.

Line Description · exactly included Qty Unit rate Mirage $ Market $ Your bid $
Division 02 · Site · civil · outdoor
2.01Clearing & grading · flag lot bowl · Zone X · no fill in AE neck1LS22,00038,000
2.02Parking · crushed/PICP · stripe · ADA · 120 stalls · south bowl only120$850/stall102,000156,000
2.03Drive · one curb cut · enter east / exit west · 4-car queue · ADA walk 6′1LS11,00020,000
2.04Utility trenches & stubs · water · sewer · 400A elec · comm · grease pit west1LS28,00048,000
2.05Stormwater SPR-1 · detention ~3,900 CF · civil PE sealed1LS35,00055,000
2.06Landscape Day 1 · portal · palms · strings · sign · north buffer1LS12,00028,000
2.07Plunge pool 15′×35′ · equipment · ≤10′ deck · key gate · no public swim525$42/SF22,00042,000
2.08Event lawn turf in court void 120′×40′4,800$1.67/SF8,00018,000
2.09Stage 32×12 + projector + tension screen · AV power · no permanent LED1LS10,00022,000
Subtotal · Site250,000427,000
Division 03 · Concrete
3.01Slab-on-grade ~12,000 SF (200×84 minus 120×40 void) · rebar · vapor · anchor template12,000$14.83/SF178,000264,000
3.02Kitchen turn-down · trenches · cloud kitchen 42×30 + chef hall 60×601LS14,00022,000
3.03Pool & stage footings · north palm court1LS5,00010,000
Subtotal · Concrete197,000296,000
Division 13 · PEMB · one shell 200×84×3
13.01PEMB package · 8 bents @ 25′ · L1 eave 16′ · portal RO 35′ · 3 roll-up RO west · IMP · hurricane-rated Jefferson16,800$40.77/SF ftpr685,0001,180,000
13.02PEMB erection · crane · bolt-up · dry-in · no roof over court void1LS155,000240,000
Subtotal · PEMB840,0001,420,000
Division 09 · L1 program · finishes @ CO
9.01Grand Arrival 75×36 · sealed conc · stone · bar MW-1 · exposed deck · NO drop ceiling2,700$9.26/SF25,00052,000
9.02Six Chef Hall 60×60 · stained conc · black spray deck · 6 concepts @ CO · 3 roll-ups operational3,600$6.94/SF25,00068,000
9.03Cloud kitchen 42×30 · quarry tile · FRP · 6 cubicles · walk-in · dish1,260$19.84/SF25,00048,000
9.04Mirage Ballroom 75×60 · black box · drape · uplight · 299 OL path4,500$3.56/SF16,00042,000
9.05Retail shell × 7 · 25×30 each · demising · slab · court door · Manhattan solid7$2,500/bay17,50035,000
9.06Retail lease-ready × 3 · LVP · paint · base electric · food-adjacent bays3$7,500/bay22,50045,000
9.07Passenger elevator · 3-stop · core 10×10 · pit · permit1each55,00082,000
9.08Manhattan facade · SF-1 glass 35×28 · stone · slat · sign · §40-447(h)1LS28,00095,000
Subtotal · L1 finishes + facade + elev214,000467,000
Division 09 · L2–L3 hotel · 48 keys · RM-1 12×28
9.10LGS framing + rough MEP · 48 identical bays · stacked wet walls · mock-up 1 first48$4,000/key192,000360,000
9.11Room finish · LVP · paint · in-room bath 3×8 each · trim · doors/windows48$3,917/key188,000480,000
Subtotal · Hotel build (excl FF&E line 12.03)380,000840,000
Division 08 · Doors · windows · roll-ups
8.01D-01 portal + D-02–04 roll-ups + 10 retail + 48 hotel + 3 RR + 6 pickup + egress1LS18,00032,000
Division 22 · Plumbing · restrooms
22.01RR-1 public 18×12 · 4 stalls · 2 lav · ADA · signature tile1bank16,50028,000
22.02RR-2 court/retail 18×12 · 4 stalls · west leg1bank15,50026,000
22.03RR-3 employee 8×10 · 2 WC · 2 lav · BOH only1bank5,5009,000
22.04Kitchen plumbing · floor sinks · hand wash · 6 lines · to grease interceptor1LS18,00032,000
22.05Grease interceptor · west spine · sized 6-concept kitchen1each9,50016,000
22.06Water heaters · hotel 48 keys + kitchen + RR load1LS9,00014,000
Subtotal · Plumbing74,000125,000
Division 23 · HVAC
23.01L1 RTUs · makeup air · chef hall · ballroom · exposed duct minimal1LS52,00098,000
23.02PTAC or per PE · 48 hotel rooms48$780/key37,44062,000
23.0328′ Type I hood · exhaust · makeup · Ansul coordination1LS28,00048,000
Subtotal · HVAC117,440208,000
Division 26 / 21 · Electrical · fire
26.01400A service · panels · branch · court lights · sign · stage · hotel · kitchen1LS68,000115,000
26.02Fire alarm · horn/strobe · addressable1LS11,50018,000
21.01NFPA 13 wet sprinkler · full shell · kitchen hood tie-in16,800$3.10/SF52,08088,000
Subtotal · Elec + fire131,580221,000
Division 11 · Kitchen equipment · Division 12 · FF&E
11.01Kitchen equipment · 6 concepts · line · prep · cold · all-electric · startup6$5,833/concept35,00095,000
12.01Grand Arrival bar equipment allowance1LS8,00018,000
12.02Ballroom · drape · chairs stack 299 · portable AV1LS10,00022,000
12.03Hotel room FF&E · bed · desk · fridge niche · TV · 48 keys @ $3,50048$3,500/key168,000240,000
12.04Chef hall furniture · tables · cream seats · marble · purple stools1LS14,00028,000
Subtotal · Equip + FF&E235,000403,000
General conditions
01.01GC supervision · temp power · cleanup · insurance · 16-week schedule16$3,500/wk56,00095,000
01.02Permit coordination · inspections · CO punch · permit fees excluded1LS12,00022,000
01.03Contingency · owner line · or include in your lines1LS49,98075,000
TOTAL GC SCOPE · DAY 1 @ CO $2,575,000 ~$3,859,000 $
+ Land (owner · not GC): $425,000 · All-in cap target: $3,000,000 · Market all-in same scope: ~$4,284,000

Restrooms · not hotel in-room · included in lines above

MarkSizeFixturesMirage $Serves
RR-118×124 stalls · 2 lav22.01 · $16,500Bar · dining · ballroom · hotel @ L1
RR-218×124 stalls · 2 lav22.02 · $15,500Retail · court · lawn
RR-38×102 WC · 2 lav22.03 · $5,500Kitchen staff only
48 in-room3×8 eachtub/shower · vanity9.11 · inclInside each hotel room · NOT public RR

Submit your bid · beat $2,575,000

Attach: completed Your Bid $ column · sub list · insurance · schedule · exceptions (if any — expect rejection if scope gaps).

PDF: scripts/build-gc-bid-sheet.sh → Desktop SEND-TO-CONTRACTOR-2D-GC-BID-SHEET.pdf · MEP/plumbing by SF: 1705-CONCEPT-2D-MEP-PLUMBING-BRIEF.html · Drawings: D2-A1-1 · D2-A2-3–6 · P2 PEMB