Building Permit Submittal Package · Jefferson Parish · Jul 2026

The real permit roadmap for the current plan — Mirage Hall 120′×60′ (A-2) + retail strip 150′×50′ at 1705 Manhattan Blvd, Harvey, LA 70058 (Jefferson Parish · MU-CD). What to file, who must seal it, who reviews it, and in what order.

CURRENT PLAN · 120×60 · 299 OL SUPERSEDES the retired New Orleans "Mirage District" checklists (Docs 11, 64) — DO NOT SUBMIT those

1 · Where & how you file

2 · Who must seal the drawings (this is non-negotiable)

Louisiana RS 37:155 sets when a Professional of Record (POR) must seal. Your building blows past every threshold.

DisciplineSeal required?Why
Architect (AOR)REQUIRED — LA-licensed architectGroup A (assembly) over 2,650 SF must be sealed by an architect. You're 7,200 SF. A civil engineer cannot stamp an assembly building in LA — it must be an architect.
Structural (SE/PE)Delegated to PEMBPEMB vendor supplies LA-stamped frame + anchor-bolt design; foundation PE stamps slab/footings/piles per geotech.
MEP (PE)Likely requiredEngineer's seal triggers when HVAC ≥ 10 tons or electrical service ≥ 600A / 480V — a 7,200 SF hall + kitchen will hit HVAC tonnage. Plan on a sealed MEP set.
Civil (PE)REQUIREDSite plan, grading, stormwater (SPR-1 · LID §33-6.26), drainage, parking geometry, curb cut — sealed civil for Site Plan Review.

Bottom line: your first hire is a Louisiana-licensed architect (AOR). They lead the set and pull in the structural/MEP/civil PEs. Nothing gets reviewed without the architect's seal + a "statement of supervision" on the first sheet.

3 · The review tracks (these run in parallel)

AgencyReviewsYou submit
JP Inspection & Code EnforcementBuilding, Mechanical, Electrical, Plumbing codeSealed A / S / M / E / P set + code data + application
JP Engineering — Site Plan ReviewSite, parking, drainage, curb cut / drivewaySealed civil site + drainage set + current survey
JP Engineering — UtilitiesWater / sewer taps, capacity, drainage tie-inUtility plan; tap applications
LA State Fire Marshal (OSFM)Life safety — NFPA 101, egress, occupant load, sprinklers, hoodPlan review application + fee + sealed set + use description
Louisiana Dept. of Health (LDH)Food service — the 6-unit cloud kitchenFood establishment plan review (kitchen layout, finishes, grease)
JP Planning Dept.Zoning clearance — MU-CD use verificationZoning clearance application (needed before operating)
DOTD (only if applicable)Curb cut if Manhattan Blvd is a state routeDOTD commercial driveway application — confirm jurisdiction of Manhattan Blvd first

4 · Submittal document checklist

#DocumentWho producesStatus
1Completed building permit application (MyGovernmentOnline) + owner/agent/architect/contractor info + LA contractor license #OwnerNeed — file online
2Current property survey / ALTA (PLS #8387 basis) with legal descriptionSurveyorHave survey; confirm current + sealed
3Geotechnical soils report (drives slab vs. piles + detention)GeotechNeed — order first (~$8–15k)
4Dimensioned site plan — parking, drainage, curb cut, setbacks (sealed civil)Civil PEA0.1 drafted — Civil PE seal C1.x
5Stormwater management plan (Jefferson SPR-1 + Parking Lot Detention + MU-CD §33-6.26 LID) + detention calcsCivil PENeed — ~3,900 CF LID target on ALTA
6Architectural set — floor plans, elevations, FF&E, schedules, life-safety (sealed architect)AORREV H7 · 26 sheets drafted — AOR seal
7Occupant-load calc (NFPA 101 / IBC 1004) — posted 299AORBasis set (299 lock)
8Structural — PEMB frame + anchor bolts (LA stamp) + foundationPEMB + PEWith vendor quote (§ order)
9MEP set — sprinkler (NFPA 13), Type I hood (NFPA 96/UL300), electrical, plumbing, HVAC/MUAMEP PE + fire subNeed — sealed MEP
10Energy code compliance (IECC 2021 / ComCheck)AOR / MEPNeed
11Accessibility (IBC Ch. 11 / ADA) — parking, restrooms, path of travelAORIn arch set
12OSFM plan review application + feeOwner / AORFile with sealed set
13LDH food establishment plan review (cloud kitchen)Owner / kitchen designerParallel track
14Zoning clearance (JP Planning · MU-CD)OwnerConfirm A-2 + parking basis
15Statement of supervision on first sheetAOROn sealed set

5 · Permit drawing sets · REV H7 (building) + REV BA (civil)

Start here: Jefferson command center · Building CD index (26 sheets) · Civil CD index (15 sheets)

Building volume · REV H7 · 26 sheets

SheetTitleByStatus
G0.1–G0.2Code summary · life safety @ 299 OLAORDRAFTED
S0.1Structural PEMB coordination · foundation · windPEMB + PECOORD DRAFTED
M0.0MEP discipline index · E/P/M/FP handoffMEP PEINDEX DRAFTED
A0.1Site plan — hall + retail + parking + curb cutAOR + CivilDRAFTED
A1.1Hall floor plan · 120×60 · zonesAORDRAFTED
A1.6–A1.8FF&E full layout · lighting/AV · court FF&EAORDRAFTED
A1.2–A1.3Retail floor · kitchen enlargedAORDRAFTED
A0.COURTCourt floor · OL 150AORDRAFTED
A1.4–A1.5Roof · reflected ceilingAORDRAFTED
A2.1–A2.3Elevations · building sectionsAORDRAFTED
A3.1–A3.7Wall · ADA RR · windows STOCK · doors STOCK · finishes · detailsAORDRAFTED
A4.1Signage & graphics scheduleAORDRAFTED
B-PARKParking worksheet · 86 min / 100 @ openAOR + CivilDRAFTED

Civil volume · REV BA · companion submittal

SheetTitleByStatus
G1.0 · A2.0General notes · survey overlay PLS #8387Civil PEDRAFTED
A0.2Parking geometry · 100 stalls · dimension authorityCivil PEDRAFTED
T1 · T-STUDY · T-CIRC · T-SIGHT · T-30Traffic circulation · analysis · sight · AutoTURNCivil PEDRAFTED
F1 · A1Fire access · ADA planCivil PEDRAFTED
C4.1 · C3.1 · L1 · C5Striping · grading/drainage · landscape · detailsCivil PEDRAFTED

Still requires professional seal (not in CD set yet)

DeliverableByStatus
Sealed M/E/P sheets · NFPA 13 · hood · ComCheckMEP PE + fire subPE TO SEAL
PEMB shop drawings + foundation calcsPEMB vendor + PEWITH VENDOR ORDER
Geotechnical reportGeotech PEORDER
Current sealed ALTAPLSCONFIRM CURRENT

REV H7 building set is drawn to permit coordination standard — every seat, STOCK opening, court FF&E, signage. AOR verifies on stamped ALTA and seals. Civil REV BA is a separate PDF volume for Site Plan Review. MEP/structural professionals attach sealed sheets; they do not redraw interior layout from scratch.

6 · Code data summary (goes on the cover sheet)

ItemValue
Occupancy groupA-2 (assembly — food/drink) · accessory B/S
Construction typeII-B (non-combustible PEMB steel) — verify w/ AOR
SprinkleredYes — NFPA 13 wet (required: >5,000 SF fire area AND >100 OL)
Gross floor area7,200 SF (120′ × 60′), 1 story, 16′ eave
Posted occupant load299 (deliberate design cap · SSoT §6)
Exits2 required + 1 framed future knockout (east)
Kitchen suppressionType I hood + UL300 (NFPA 96)
ParkingCZO Table 22-1 basis · 86 code min · 100 striped @ open (48 hall + 38 retail + ADA)
ZoningJefferson Parish MU-CD

7 · Sequence & realistic timeline

  1. Hire the AOR (LA architect) — required, leads the set. week 0
  2. Survey + geotech — order immediately; geotech decides foundation. 2–4 wks
  3. Zoning clearance + pre-app (JP Planning) — confirm A-2 use, parking, single curb cut. 2–4 wks
  4. Design + seal — AOR + civil + MEP + PEMB produce the sealed set. 2–4 months
  5. Parallel plan review — JP Inspection/Code + Engineering Site Plan Review + OSFM + LDH. ~1–3 months (10-day cycles + comment responses)
  6. Permit issued → order PEMB kit → slab → erect → MEP rough → inspections → C/O.

Honest total to permit-in-hand: ~5–8 months from hiring the architect, assuming fast comment turnaround. The single curb cut + A-2 assembly are the items reviewers scrutinize most — the 299 cap is what keeps that review smooth.

8 · Fee ballparks (verify at submittal)

FeeRough range
JP building permit (by construction value)~$3k–$7k
Trade permits (M / E / P)~$1k–$3k combined
OSFM plan review~$0.5k–$2k (by SF/value)
Engineering site plan / driveway review~$0.5k–$2k
LDH food plan review~$0.2k–$0.6k
Impact / drainage / utility tapsvaries — ask Utilities
Design fees (AOR + PEs) — not permit feesthe real cost: ~$40k–$90k (in the GC budget soft costs)

9 · Cross-refs